CALIFORNIA: High-speed rail construction delayed
San Jose Mercury News ^ | 2/29/12 | Mike Rosenberg

Posted on 02/29/2012 8:58:36 PM PST by SmithL

With a long-standing federal deadline breathing down their necks, California's polarizing $100 billion bullet train suddenly got a much-needed reprieve Wednesday after the Obama administration eased the target for starting construction.

For years, state high-speed rail leaders aimed for a September 2012 groundbreaking to meet the assumed deadline for the federal stimulus program, which funded about one-third of the $6 billion first leg of track.

But in a statement Wednesday, federal rail officials said the train "is making continual progress" and for the first time revealed that the law does not specifically require a deadline to start construction. Technically, it mandates the funds be "obligated" by September, and for the project to be finished by September 2017.

State rail officials still hope to start building by the end of this year but could begin in early 2013, giving them extra time to work on an unprecedented project that some state and local leaders fear was being rushed to meet the federal deadlines.

"If this is the first step down a $100 billion path, it better be the right first step," said state Sen. Joe Simitian, D-Palo Alto, one of the lawmakers who has called for the project to slow down. "I think it's important for all of us to resist being hurried into a decision we might later regret, given the multi-billion dollar consequences."

At its Thursday board meeting, the California High-Speed Rail Authority will detail the latest construction schedule for the first stretch of track in the Central Valley. A skeptical Legislature still must approve the funding, however.

(Excerpt) Read more at mercurynews.com ...


TOPICS: Business/Economy; Extended News; Government; US: California
KEYWORDS: goldenstate; highspeedrail; pork; yourtaxdollarsatwork

1 posted on 02/29/2012 8:58:45 PM PST by SmithL
[ Post Reply | Private Reply | View Replies]

To: SmithL

$100 billion? Wasn’t it originally supposed to cost $30 billion?


2 posted on 02/29/2012 9:03:33 PM PST by VeniVidiVici
[ Post Reply | Private Reply | To 1 | View Replies]

To: SmithL

Obama needs to get some bigger toilets designed to flush the taxpayer’s money down.


3 posted on 02/29/2012 9:04:40 PM PST by Proud2BeRight
[ Post Reply | Private Reply | To 1 | View Replies]

To: Proud2BeRight

Cool.. Let’s delay it for a while....

Then, cancel it altogether.


4 posted on 02/29/2012 9:08:47 PM PST by CarmichaelPatriot
[ Post Reply | Private Reply | To 3 | View Replies]

To: SmithL

Something tells me various environmental agencies and groups were a little less stringent on any impact studies and reports, compared to say a new power plant, commercial building, mall, factory, etc/


5 posted on 02/29/2012 9:12:09 PM PST by matt04
[ Post Reply | Private Reply | To 1 | View Replies]

To: VeniVidiVici
$100 billion? Wasn’t it originally supposed to cost $30 billion?

It was originally estimated to cost somewhere between $30 and $40 million (not sure of the exact figure). A few years in, the cost estimates were raised (almost tripled), completion dates were significantly extended, and ridership estimates greatly reduced. God only knows how many more changes will occur to those "estimates" over the course of the project.

6 posted on 02/29/2012 9:15:53 PM PST by Bob
[ Post Reply | Private Reply | To 2 | View Replies]

To: SmithL

Tijuana to LA?


7 posted on 02/29/2012 9:32:54 PM PST by Gaffer
[ Post Reply | Private Reply | To 1 | View Replies]

To: SmithL

How much would it cost for a High Speed Stagecoach?

Pray for America


8 posted on 02/29/2012 9:52:10 PM PST by bray (More Batting Practice for the Bambino)
[ Post Reply | Private Reply | To 1 | View Replies]

To: SmithL

Have these clowns ever heard of a gantt chart??
If you can’t tell on any given day if your project is on target or not, you’ve got a CF on your hands.


9 posted on 02/29/2012 9:52:33 PM PST by bossmechanic (If all else fails, hit it with a hammer)
[ Post Reply | Private Reply | To 1 | View Replies]

To: Gaffer

“Tijuana to LA?”

Sadly, NO, that would be a paying route.The “initial section” will be between Fresno and Bakersfield ( or something close to that). That’s all farmland, no people ( except farm workers) but it’s the easiest part of the build,


10 posted on 02/29/2012 10:05:32 PM PST by vette6387
[ Post Reply | Private Reply | To 7 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
News/Activism
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson