Here’s the reality on “shovel ready” projects.
Public works projects take, at minimum, 3 years. I’m talking even for a minor intersection improvement.
Year 1 - Design
Year 2 - Right of Way Acquisition
Year 3 - You actually build it
What everyone wants for political purposes are the blue collar jobs in year 3. Unfortunately no one sees the white collar stuff, so “nothing” happens for 2 years.
Add time for bigger projects.
Very few projects are already at the stage where 1 and 2 above are already done, just awaiting final funding to build.