Free Republic
Browse · Search
News/Activism
Topics · Post Article

Skip to comments.

I-40 OK Bridge Reopens Ahead Of Schedule And WAY Ahead Of Estimates
Oklahoma Department Of Transportation ^ | 07/29/02 | OK-DOT Stann Minion

Posted on 08/05/2002 10:16:54 AM PDT by Wright is right!

Webbers Falls I-40 Bridge Opens Ahead Of Schedule

Careful planning, fast action and hard work combined to allow the reopening of the I-40 bridge at Webbers Falls even earlier than the contractor’s ambitious estimate.

After a brief ceremony on July 29 that included remarks from transportation and government officials and a moment of silence in memory of the victims of the accident, traffic began rolling in both directions. It was more than a week earlier than the deadline date set in the construction contract.

“Everyone connected with this project has given a maximum effort from the very beginning,” ODOT Director Gary Ridley said. “I’m tremendously proud of the way our ODOT people responded to this crisis and the long, hard hours they worked. The many organizations we have partnered with on this project have also given the utmost in work and cooperation.

“Our contractor, Gilbert Central, did an incredible job of organizing and carrying out a project that would normally take twice as long.

“With a major coast-to-coast traffic artery interrupted by the bridge disaster, rapid reconstruction was imperative, and all parties came through brilliantly. We had a safe, well-coordinated project and an early completion on a sound, properly designed structure,” Ridley said.

The bridge was struck by two barges moving upstream outside the marked channel of the Arkansas River navigation system on the morning of May 26. The falling sections of the bridge resulted in 14 motorists being killed.

“That those people died at this place will always be in the background of our thoughts about the bridge,” Ridley said.

In response to the disaster, ODOT set up detours and immediately began planning for the reconstruction of nearly 600 feet of the damaged bridge.

With unprecedented speed, a special pre-bid meeting was called at the bridge site, bids were opened and the contract awarded to Gilbert Central of Fort Worth. The contractor bid a time of 57 days for the bridge to reopen. The clock started running at 6 p.m. the day the contract was awarded, June 12.

Wheels were already turning to get the money needed for the project without crippling ODOT’s other construction projects. The Federal Highway Administration and the Oklahoma Congressional delegation worked to come up with federal money, even as engineers refined the material and construction requirements for the job.

FHWA Assistant Division Administrator Lubin Quinones noted the close communication and cooperation between government agencies and the private sector. “This is a very gratifying example of what can happen when everyone works together with a critical objective,” he said.

A trio of retired ODOT engineers, representing over a century of construction experience between them, was called upon to head up the specially-established Webbers Falls Residency to oversee and coordinate the project.

Unlike a permanent residency, that handles a number of projects in several counties, the Webbers Falls office was set up solely for the I-40 bridge project.

One of the features of the contract was an incentive/disincentive clause. For every hour the contractor beat the reopening deadline, $6,000 would be added to the payoff. For every hour over the deadline, $6,000 would be deducted.

By beating the deadline by 10 days, Gilbert Central earned an extra million and a half dollars.

There is still work to be done at the site. Periodic lane closures will take place for striping and other minor tasks. The contractor will be making those finishing touches for a while, but reopening the bridge in a safe, operational condition was the critical factor and the basis for the incentive deadline. More time is built in to complete the rest of the project.

“This was a unique operation,” Ridley noted. “I believe the steps we took in repairing the bridge were the correct ones, and showed what can be done when you really have to respond quickly to a serious situation.”
------------------------


TOPICS: Front Page News; News/Current Events
KEYWORDS: i40bridgereopens
The source URL above will take you to the ODOT page where there are links to photos shot almost every day of the reconstruction. You can see some of the techniques they used to make this bridge stronger than the old one. They also pre-fabbed rebar work off-site instead of the laborious and slow process of doing it on-site once the beams are up. Interesting....

Michael

1 posted on 08/05/2002 10:16:54 AM PDT by Wright is right!
[ Post Reply | Private Reply | View Replies]

To: Wright is right!
Wow. It took forever to re-open I-95 in CT when a bridge fell in 1983.
2 posted on 08/05/2002 10:29:58 AM PDT by Rodney King
[ Post Reply | Private Reply | To 1 | View Replies]

To: Wright is right!
Bump for travelers everywhere...

Michael

3 posted on 08/05/2002 10:30:05 AM PDT by Wright is right!
[ Post Reply | Private Reply | To 1 | View Replies]

To: Wright is right!
The only problem is that Ark. and Tenn. has the rest of I40 torn up for repairs, so don't expect to save any time. Spoken from bitter experience.
4 posted on 08/05/2002 11:46:10 AM PDT by parcel_of_rogues
[ Post Reply | Private Reply | To 1 | View Replies]

To: Wright is right!
I went through the area on July 17th and saw a semi turn over on the detour west if Sallisaw. This thing needed to be done asap. As for the rest of I-40 through Arkansas, it was a nightmare. I dodged Memphis by going south from Brinkley over to Helena, turning north on 61 and caught 302 in North Mississippi. Even with that kind of out of the way drive I saved about an hour and a half.
5 posted on 08/05/2002 2:37:32 PM PDT by vetvetdoug
[ Post Reply | Private Reply | To 1 | View Replies]

To: Rodney King
Which bridge in Connecticut fell? (I lived in New Haven 1980-81 and 1991-4.)
6 posted on 08/05/2002 2:43:51 PM PDT by aristeides
[ Post Reply | Private Reply | To 2 | View Replies]

To: aristeides
I-95 in Greenwich. A 100 foot span collapsed.
7 posted on 08/05/2002 3:21:38 PM PDT by Rodney King
[ Post Reply | Private Reply | To 6 | View Replies]

To: Wright is right!
The state of California said Screw diversity when we had the 94 quake. As you recall we had some interchanges down. They gave the contract to the best guy and he brought it in 2 months ahead of schedule and recieved a handsome bonus. We just said okay now why did it take a couple decades to build the century freeway.
8 posted on 08/05/2002 7:50:45 PM PDT by Walkingfeather
[ Post Reply | Private Reply | To 1 | View Replies]

Disclaimer: Opinions posted on Free Republic are those of the individual posters and do not necessarily represent the opinion of Free Republic or its management. All materials posted herein are protected by copyright law and the exemption for fair use of copyrighted works.

Free Republic
Browse · Search
News/Activism
Topics · Post Article

FreeRepublic, LLC, PO BOX 9771, FRESNO, CA 93794
FreeRepublic.com is powered by software copyright 2000-2008 John Robinson